3COM certification 3COM
Adobe certification Adobe
Apple certification Apple
Avaya certification Avaya
BEA certification BEA Systems
Business Objects certification Business Objects
Check Point certification Check Point
Cisco certification Cisco
Citrix certification Citrix
CIW certification CIW
CompTIA certification CompTIA
CWNP certification CWNP
EC-Council certification EC-Council
EMC certification EMC
Exam Express certification Exam Express
Exin certification Exin
F5 Networks certification F5 Networks
HDI certification HDI
HP certification HP
Hitachi certification Hitachi
IBM certification IBM
ISC certification ISC
ISEB certification ISEB
Juniper certification Juniper Networks
Lotus certification Lotus
LPI certification LPI
Microsoft certification Microsoft
Mile2 certification Mile2
Network Appliance certification Network Appliance
Nortel certification Nortel
Novell certification Novell
Oracle certification Oracle
PMI certification PMI
RedHat certification RedHat
SAIR certification SAIR
SAS certification SAS Institute
SNIA certification SNIA
Sun certification Sun
Sybase certification Sybase
Symantec certification Symantec
Teradata certification Teradata
Tibco certification Tibco
Veritas certification Veritas
VMware certification VMware
All Exams

ISEB BH0-002 Exam - PassITexam.com

Free BH0-002 Sample Questions:

Q: 1
The Internal Rate of Return is:

A. The Discount Rate which produces the highest NPV
B. The Discount Rate which produces the lowest NPV
C. The Discount Rate which matches the normal bank interest rate
D. The Discount Rate which produces a zero NPV

Answer: D

Q: 2
What is product based planning?

A. A technique that marketing departments use to launch new products and services.
B. A technique that seeks to identify tasks and activities
C. A technique that monitors the progress of the project
D. A technique that concentrates on the identification and definition of what the project is to deliver

Answer: D

Q: 3
Complete the following statement choosing the most appropriate option from those below. “The design authority is responsible for?”

A. Co-ordinating the overall programme and constituent projects
B. The programme
C. Business integrity within the programme
D. Technical integrity across projects

Answer: D

Q: 4
End Project Reviews should be used to:

A. Identify who was responsible for any failures
B. Consider support requirements
C. Capture lessons learned for future projects of a similar nature
D. Agree when the project team can be released for other work

Answer: C

Q: 5
Which of the following is NOT typically a component of a Project Initiation Document / Terms of Reference?

A. Detailed Analysis
B. Timescales
C. Risks
D. Objectives

Answer: A

Q: 6
Which level of plan forms the basis of the project manager’s day to day control?

A. Stage / Tranche
B. Individual
C. Project
D. Team

Answer: A

Q: 7
The primary objective of the configuration control process is to ensure that deliverables / products are:

A. Not changed once completed without approval
B. Logged at inception
C. Audited following changes
D. Given an unique ID

Answer: A

Q: 8
In a formal Quality Review who does NOT have an automatic right of attendance?

A. Administrator / Recorder
B. Qualified Reviewers
C. Deliverable producer or representative
D. Project Manager

Answer: D

Q: 9
Which of the following is NOT a formal Configuration Management process?

A. Control
B. Audits or Verification
C. Validation
D. Identification

Answer: C

Q: 10
The fact that a “today” is not worth the same as “ in the future results in the application of what to future monies?

A. Internal Rate of Return
B. Contingency
C. Inflation
D. Discount rate

Answer: D

Q: 11
“A typical plan at the business or strategy level will include the major deliverables to fulfill the strategy, the resource expenditure, a plan for the achievement of benefits, and” Which of the following completes this statement?

A. The programme reporting arrangements to be used
B. A description of the techniques used in the preparation of the plans
C. The plans of the portfolio projects
D. The major milestones or events

Answer: B

Q: 12
Click on the Exhibit button.
Click the Calculator button.

In Chart 1, at the Month 7 set of figures, what is the Schedule Variance? Is it:

A. -0
B. -20
C. -1 Month
D. +1 Month

Answer: A

Q: 13
The overall responsibility for monitoring and managing the project risk log should be taken by which role?

A. Project Manager
B. Risk Owner
C. Project Sponsor
D. Project Support Co-ordinator

Answer: A

Q: 14
The resolution of an Exception situation is the ultimate responsibility of:

A. The person who discovered the problem
B. The Users
C. The Project Sponsor/Board
D. The Project Manager

Answer: C

Q: 15
The business case is assessed:

A. Throughout the project
B. During feasibility
C. At major milestones
D. When major issues are encountered

Answer: C